icon/64x64/regionalcooperation Regional cooperation

Uttarakhand is building a dam over an area larger than Chandigarh

The proposed India-Nepal 5,040 MW Pancheshwar project aims to produce more power than all existing dams in the state, and it is generating massive protests
<p>Protestors march in support of public hearings against the proposed project [image by: Hridayesh Joshi]</p>

Protestors march in support of public hearings against the proposed project [image by: Hridayesh Joshi]

Slogans rent the air as around 1,000 people gathered outside Vikas Bhawan in the Pithoragarh district headquarters of Uttarakhand on August 11. They held up banners that read “Bina jaankari kaise jansunwai” (what kind of a public hearing is this without informing us), “Baandh nahee vikas chahiye” (we need development, not a dam), and “Ye jansunwai dhokha hai” (this public hearing is fraud). The police held them back.

Inside, a public hearing on the environmental impact of the proposed 5,040-megawatt Pancheshwar hydropower dam – with the potential to produce more power than all existing dams in the state put together – was in progress. Under law, such hearings are to be conducted after an environment impact assessment report of the project has been prepared and put before the people who would be affected by the project in a language they can read. It is a consultative process. The district administration takes note of people opposed to or in favour of the project and any other concerns. Then they move on to the next public hearing. Finally, they send a report to the Central government.

The first public hearing on the Pancheshwar dam was held in adjoining Champawat district on August 9. The third and final one was conducted in Almora on August 17.

In Pithoragarh, there were angry voices inside Vikas Bhawan too. They questioned the logic of holding a public hearing in the upper Himalayas in peak monsoon, when the rains have cut off several villages and landslides have gobbled up entire roads.

“Many villagers could not get here,” said Sanjay, who had come from Bagrihaat village 70 km away. “We could make it but hundreds of our people got stranded on the way.”

Days later, on August 14, two cloud bursts left eight people dead in Pithoragarh while 25 are still missing.

Yet, the administration was set on completing the public hearings within this time frame. Ashish Chauhan, the officiating district magistrate, said, “I gave orders to my officers to open the roads on a priority basis. We know these are landslide zones and this is monsoon season but still we are trying our best.”

The state government’s hurry may have something to do with the Centre’s sudden and favourable U-turn on the project. In 2016, an expert panel of the Union Environment and Forests Ministry had sought a joint mechanism with Nepal to assess the impact of the dam on both sides of the border. But in May this year, it relented and said such a move would delay the process, paving the way for the public hearings.

Pithoragarh residents protest outside the venue of a public hearing on the dam project on August 11 [image by: Hridayesh Joshi]

Not just a dam

Pancheshwar is not just the biggest dam to be planned in Uttarakhand but also a commitment made by India to Nepal under the 1996 Mahakali Treaty. The long-pending project got a fillip when Prime Minister Narendra Modi visited Nepal in 2014. A Pancheshwar Development Authority was set up consequently to finalise the project.

The project is to come up near the Pancheshwar temple, 2.5 km downstream of the confluence of the Mahakali and Sarju rivers. It entails two dams working in tandem. The main Pancheshwar dam would rise 311 metres and the second one downstream would be 81 metres high.

The project is expected to submerge 11,600 hectares of mountain area – a land mass larger than Chandigarh (11,400 hectares)in five seismic zones. Of this area, 7,600 hectares would lie in the three districts of Uttarakhand and the rest in Nepal.

In all, the authorities plan to acquire 9,100 hectares of land in Uttarakhand and 5,000 hectares in Nepal.

According to project developers, close to 30,000 families spread over 62 villages in Uttarakhand stand to lose their land. They have not yet assessed how many livelihoods would be impacted.

Some 30,000 families in over 62 villages in Uttarakhand stand to lose their land to the project [image by: Hridayesh Joshi]

‘Tamasha, not public hearing’

At the public hearing in Pithoragarh, people expressed their anger and anxiety over the project. Some also objected to the presence of policemen and leaders of the ruling Bharatiya Janata Party on the dais. The regulations do not allow this. Harish Dhami, a Congress MLA, almost came to blows with BJP MLA Bishan Singh Chuphal and the two had to be pulled apart.

“This is not a public hearing. It is a tamasha [performance],” remarked Uttarakhand Kranti Dal leader Kashi Singh Airy. “The officers of authority and the administration are not speaking and members of the Bharatiya Janata Party are pushing us out of the room. They are answering people’s queries. Are they authorised to do this?”

One attendant shouted, “We want only officers to hear us. These are leaders and thekedars [contractors] who will benefit from the project.”

Another wondered aloud how the project report had been prepared. “Have you ever come to our village?” he asked. “How did you write this report?”

Yet another protestor spoke of being unable to read the report, saying: “You should make this entire report available to us in Hindi before such a hearing.”

BJP leaders on the dais at the public hearing in Pithoragarh [image by: Hridayesh Joshi]
But not everyone in the three districts is opposed to the dam. Some hope it will change the poverty, lack of employment and high migration rate in the region.

“Villagers are ready to give land and we will give them good compensation,” state minister Prakash Pant told Scroll.in over telephone. “At present, we have estimated Rs 10,700 crores for relief and rehabilitation. We will increase the money if required.”

It is also true that whether it is the BJP or the Congress, when in power, both actively promote the case for big dams in the hill state. This despite a government expert panel’s conclusion that dams had exacerbated the devastation caused by the Kedarnath floods in 2013, in which over 5,000 people were reportedly killed.

However, apprehension outweighed optimism at the hearing venue.

Furthermore, the Pancheshwar dam is a threat to small projects for regional development. In Rasyuna village on the banks of the Sarju river, for instance, villagers have come together to plan their own 1-megawatt mini hydro project under the state’s policy to promote small dams. Their project report estimates that the village would earn Rs 16 lakhs to Rs 20 lakhs a month from such a dam and employ around 100 people. But now they have been told that the Pancheshwar dam will submerge the site.

Even for those willing to consider the project, past experiences with resettlement and rehabilitation do not inspire much confidence.

“We know neither our demands will be met, nor will we get adequate compensation. Our children will be homeless,” said 52-year-old Janaki Devi, who had come from the border town of Jauljeebi 65 km away. “Such promises [by government] are never fulfilled. We know the government cheats. In our vicinity, an entire village was washed away last year [after a cloud burst] and not a single family was rehabilitated.”

Rama Devi of Jhulaghat, another village that would be submerged by the Pancheshwar dam, said, “We have no clear idea where we will go. Let us see what happens.”

Attendants protest the presence of policemen and leaders of the ruling BJP at the hearing venue [image by: Rohit Joshi]

More questions

Experts acknowledged that rehabilitation would be a challenge. “Governments talk about relocating people but there is hardly any useful land left available in Uttarakhand,” said Shekhar Pathak, an academic who has researched the history of the western Himalayas for decades.

Activists questioned the clearance process and the logic of holding public hearings during the monsoon.

In a letter to the Pithoragarh district magistrate, the South Asia Network for Dams, River and People said, “The public hearing needs to be conducted in a central location of the project affected area and not in the district headquarters, like the way it is planned now.”

Himanshu Thakkar of the South Asia Network pointed to the risks of building a dam in a seismically sensitive region. “The environment impact assessment is a fundamentally flawed, inadequate and shoddy piece of work,” he said. “It has been conducted only for the Indian part [leaving Nepal aside] in violation of international norms. The agency that prepared the assessment answers to the Union Ministry of Water Resources, which is the project proponent. This is not an independent environment impact assessment.”

With the process of public hearings completed, the government is well on its way to appraising the project. The decision now lies with the Environment and Forests Ministry. Or does it?

Prime Minister Narendra Modi has already extolled the virtues of the project, promising it will bring employment and stop migration. “Uttarakhand’s water has power and electricity,” he told a public gathering in the state in February. “Just like the environment of the state is powerful. We are starting work along with Nepal on the Pancheshwar project. It will cost Rs 34,000 crores. There is a likelihood of people in this region getting jobs. The power that will be generated will be such that not only will it do away with the darkness in Uttarakhand but also in a large part of the rest of the country.”

He is not the first prime minister to speak in favour of a project before it has been appraised for its environmental impact – a statutory requirement. Legally, the environment impact appraisal can lead to the rejection of a project too. But, that is just the law.

This article was first published in Scroll.

Comments (3)

The names of the villages which will submerged under water or come under area of dam as well as to be affected has not been made public. It should be made public.

Pancheshwar Dam is a boon for India and Nepal.The rock formations are competent.The problem lies in the river section where a FAULT has been located by drillinhg.I have done detail Geolgical investigtion for the Project in 1971, when Iwas in G.S.I
H.M.Dayal

Resettle people in haldawni or dehradun or if ppl wants to live in hills then find them place to move like incase of tehri also provide compensatation to restart life in city or new place.

Add a comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.